The project Feasibility Study began in the Summer of 2016 and was completed in the Spring of 2018. On June 27, 2018, the MSBA voted to approve the City of Lowell proceeding into schematic design for an addition and renovation project at the Lowell High School. Schematic Design was conducted from July 2018 through February 2019. On June 7, 2019 the City entered into a Project, Scope and Budget Agreement with the MSBA. The Construction Document Design was conducted from the Spring of 2019 through February 2021. The main Project Bid issued in March 2021.