Weekly Project Schedule

Past Week of July 31st: 
  

• School Building Committee Meeting (Thursday 8/3)


 

  

Current Week of August 7th:

 
• Start Schematic Design MSBA Module 4 (pending authorization from City to proceed)
   

Week of August 14th:

 
 • Schematic Design MSBA Module 4 - ongoing
Project Schedule Summary July 21, 2017
MSBA Facilities Assessment Subcommittee Meeting July 27,2017
Start of Schematic Design July 28, 2017
MSBA Board Meeting - PSR Approval August 23, 2017
City Council Approval of Schematic Design and Budget March 1, 2018
Schematic Design Submittal to MSBA (subject to MSBA 2018 Schedule) March 22, 2018
DESE Review March - July 2018
MSBA Board Meeting - Project Scope and Budget Approval May 9, 2018 (TBD)
Project Funding Appropriation by City Council (120 days allowed) April - July 2018
Construction Manager Hiring Process June - August 2018
Design Development Submission to MSBA (based on 6/1/18 Des Dev Start) January 2019
Early Bid Package May - June 2019
Start Construction (site work and structural steel) July 2019
60 % Construction Documents Submission to MSBA August 2019
90% Construction Documents Submission to MSBA October 2019
100% Construction Documents Submission to MSBA December 2019
100% CD Bid Package January - February 2020
Start Construction March 2020
Project Substantial Completion June 2022
Move in New School August 2022
Closeout Project September 2022 - April 2023

Please note: Schedule is estimated based on best information available as of July 2017 and subject to change.